Cold Storage facilities are designed to keep stored commodities at various temperature levels. Some production or process areas are included in the better qualities.
Sharp freezers, freezer rooms, offices, production or process areas are included in the better qualities. The front elevation will have some ornamental detail and an office/store front type entry. Lower qualities have cooler storage areas, few partitions and small office areas that are very plain with very little or any front entry trim or ornamentation.
Cold Storage facilities have specialized cooling/freezing equipment. You should use HVAC type 617 (Complete HVAC) for the HVAC in this occupancy, selecting the quality from the following:
Low: Cooled Air Only
Average: Cooler/Chilled Air
Good: Chiller/Freezer
Excellent: Freezer/Sharp Freeze
Availability of Elevators by Area for this occupancy: No
Marshall Valuation Service sections: 14 and 44.
|
|
|
|
|
Class |
|
|
|
|
Quality |
A |
B |
C |
D |
H |
M |
P |
S |
W |
Low |
45 |
45 |
40 |
35 |
-- |
-- |
35 |
35 |
-- |
Average |
50 |
50 |
45 |
40 |
-- |
-- |
40 |
40 |
-- |
Good |
50 |
50 |
45 |
40 |
-- |
-- |
40 |
40 |
-- |
Excellent |
55 |
55 |
50 |
45 |
-- |
-- |
45 |
45 |
-- |
Class A (Fireproof Structural Steel Frame): and Class B (Reinforced Concrete Frame):
Quality |
Exterior Walls |
Interior Finish |
Mechanicals |
HVAC |
Average |
Brick, block, concrete panels, storefront entry, fully insulated |
Chilled and freezer rooms, good offices and support areas |
Adequate lighting, plumbing and drains, some power outlets |
Complete HVAC. |
Good |
Face brick, concrete panels, good facade, heavily insulated |
Frozen foods, some good offices or production, sharp freeze, cooler areas |
Good lighting & plumbing, outlets and drains |
Complete HVAC. |
Class C (Masonry Bearing Walls):
Quality |
Exterior Walls |
Interior Finish |
Mechanicals |
HVAC |
Low |
Block, tilt-up, very plain, light construction, exposed ceiling insulation |
Cooler storage, unfinished, few partitions, small office |
Minimum lighting & plumbing |
Complete HVAC. |
Fair |
Block tilt-up, sealed ceiling and wall insulation |
Cooler, controlled atmosphere, sealed rooms and slab, small office |
Adequate electrical, minimum plumbing |
Complete low-cost H.V.A.C |
Average |
Steel or wood frame or bearing walls, block or tilt-up, insulated |
Cooler and chilled rooms, some distribution offices and finish |
Adequate lighting & plumbing |
Complete HVAC. |
Good |
Tilt-up, steel frame, good block, or tapered girders, heavily insulated |
Chilled and freezer rooms, good offices and support areas |
Good lighting, adequate plumbing and drains, some power outlets |
Complete HVAC. |
Excellent |
Best block, tilt-up, good storefront, heavy floor, wall, roof insulation |
Frozen foods, some good offices or production, sharp freeze, cooler areas |
Good lighting & plumbing, outlets and drains |
Complete HVAC. |
Class D (Wood or Steel Framed Exterior Walls):
Quality |
Exterior Walls |
Interior Finish |
Mechanicals |
HVAC |
Low |
Stucco or siding on wood, insulated, exposed ceiling insulation |
Cooler storage, unfinished, few partitions, small office |
Minimum lighting & plumbing |
Complete HVAC. |
Average |
Stucco on wood frame, wood trusses, fully insulated |
Cooler and chilled rooms, some distribution offices and finish |
Adequate lighting & plumbing |
Complete HVAC. |
Quality |
Exterior Walls |
Interior Finish |
Mechanicals |
HVAC |
Low |
Pole frame, metal siding, lined, exposed ceiling insulation |
Cooler storage, unfinished, few partitions, small office |
Minimum lighting & plumbing |
Complete HVAC. |
Average |
Pole frame, good insulated siding or sandwich panels, good roof |
Cooler and chilled rooms, some distribution offices and finish |
Adequate lighting & plumbing |
Complete HVAC. |
Class S (Metal Frame and Walls):
Quality |
Exterior Walls |
Interior Finish |
Mechanicals |
HVAC |
Low |
Pre-engineered frame, metal siding, lined, exposed ceiling insulation |
Cooler storage, unfinished, few partitions, small office |
Minimum lighting & plumbing |
Complete HVAC. |
Fair |
Pre-engineered metal lined and sealed wall and ceiling insulation |
Cooler, controlled atmosphere, sealed rooms and slab, small office |
Adequate electrical, minimum plumbing |
Complete low-cost H.V.A.C. |
Average |
Rigid steel frame, insulated siding or sandwich panels, good roof |
Cooler and chilled rooms, some distribution offices and finish |
Adequate lighting & plumbing |
Complete HVAC. |
Good |
Good steel frame, sandwich panels, fenestration, heavily insulated |
Chilled and freezer rooms, good offices and support areas |
Good lighting, adequate plumbing and drains, some power outlets |
Complete HVAC. |
Excellent |
Good steel frame, insulated panel walls and roof, good facade |
Frozen foods, some good offices or production, sharp freeze, cooler areas |
Good lighting & plumbing, outlets and drains |
Complete HVAC. |