CEB Concrete Column Footings, Steel Column, Light Pre-Engineered

Concrete footings to support light, pre-engineered, structural steel frame buildings where there is no continuous foundation.

Included in Cost

Excavation, forming, reinforcing, concrete and backfill.

Quality Selection

Consider the following when selecting a quality:

Load supported: The greater the load, the higher the quality.

Size and shape: The higher the ratio of the perimeter to floor area, the higher the quality.

Load-bearing capacity of the soil: The lower the capacity, the higher the quality.

Topography: Stepped foundations require a higher quality.

Climate: The deeper the frost line, the higher the quality.

Entry Information

Enter the following for this component:

Percent of Total Floor Area: 1 – 100, or
Floor Area (Square Feet)

Construction System

Foundation

Typical Use

Class C, D and S Farm occupancies with Steel Columns