818 Concrete, Tilt up

Generally used in large, one story structures (industrial buildings). The wall section is formed on top of a concrete slab floor structure. A vapor barrier is used between the slab and the to be poured wall section, so that when the wall section is poured with concrete, the wall and slab do not bond together. Once the concrete in the section is cured, it is lifted into place on top of the foundation by a crane. These walls are usually reinforced.

Entry Information

Enter the following for this component:

Percent of Wall Area: 1 - 100

Construction System

Exterior Walls